Many families in Kharar and Mohali start building after Diwali. What to have ready before the first day on site: papers, budget, drawings, contract, water and power, and a start date the crew can keep.
Why so many families start after Diwali
Diwali falls on 8 November in 2026. For many families in Kharar and Mohali it is the natural point to begin: the festival is behind them, the bhoomi pujan is planned for the weeks after, and the cool, dry months ahead suit digging, foundations and brickwork.
A good start depends less on the date than on what is ready on the day. This checklist covers what to settle before work begins, so the first week on site is not spent waiting for papers, drawings or water.
1. Papers in hand, not in progress
Before the first trench, keep the originals and copies of:
- Registered sale deed
- Fard/Jamabandi with mutation
- Non-encumbrance certificate or search report
Have them checked by a lawyer and the entries confirmed at the tehsil office, even if you bought the plot years ago. Building work should begin only once your building plan is approved by the authority for your plot, which is GMADA or the local municipal council depending on where it lies. Your architect confirms which one applies and what it asks for; our note on GMADA plot rules covers the background.
2. A budget range you have seen on paper
A house costs ₹2,000 to ₹4,500 per sq ft of covered area, materials and labour included, GST extra, depending on the finish tier. Put your plot size and the number of floors into the construction cost calculator to get a range for each tier, or read the worked example in what it costs to build on a 200 sq yd plot. The rate card was reviewed on 2026-09-24.
Then price the items a turnkey quotation does not include, because they arrive early in the build:
- Interiors beyond the quotation (wardrobes, modular kitchen unless quoted, furniture)
- Boundary wall and gate, unless quoted
- Government approval fees and water/electricity connection charges
- Plot levelling, demolition of existing structures and soil testing
- GST
3. Drawings before digging
Excavation should start from final drawings, not a sketch: the architectural drawings, the structural drawings from a structural engineer, and the electrical and plumbing layout. Changing a column or a staircase on paper costs nothing; changing it after the foundation does. If your engineer asks for a soil test, arrange it before the drawings are final. It is outside a turnkey quotation, as listed above.
4. Quotation and contract signed before the pujan
Ask for the itemised quotation, the specification sheet for your tier and the drawing list, and read them side by side with the contract. What a turnkey quotation includes and the questions to ask a builder before you sign walk through what to check. Our standing terms:
- Stage-wise payments against milestones; the schedule is set out in your contract.
- The construction timeline depends on plot size, floors and finish, and is written into your contract.
- Any change of scope or material is priced and approved by you in writing before work proceeds.
5. A site that is ready to work on
- Temporary water and electricity in place. The connection charges sit outside the quotation, so apply early.
- The plot cleared and levelled, and any old structure removed; these are also outside the quotation.
- Space to stack bricks, sand and steel off the road, and a lockable store for cement.
- A word with the neighbours about access, parking for trucks and the shared wall.
6. A start date the crew can keep
Many site workers travel home for Diwali and Chhath and return over the following weeks. Agree the start date with your builder instead of fixing the day after Diwali, and ask who supervises the site and when the crew is confirmed. A start a little later with a full crew moves faster than an early start with half of one.
7. Know what winter changes on site
The cool, dry weather after Diwali suits excavation, foundations and brickwork. Cold days and fog slow the curing of concrete and plaster, so the site engineer plans slab pours and curing around the weather in December and January. Ask how they will handle it before work starts, not when the first slab is due.
If you live abroad, the order of work is the same; building your house in Punjab from abroad covers signing, payments and updates from another time zone.
The checklist
- Registered sale deed, Fard/Jamabandi with mutation, Non-encumbrance certificate or search report: originals checked by a lawyer.
- Building plan approved by the authority for your plot.
- Budget range from the calculator for your tier, with the excluded items priced separately.
- Architectural, structural, electrical and plumbing drawings final.
- Quotation, specification sheet and contract read and signed.
- Temporary water and electricity arranged, plot cleared and levelled, storage space marked.
- Start date agreed with the builder and the crew confirmed.
Still looking for the plot? See the plots for sale we hold, with the papers we have seen for each one. Already have one? Start with the calculator or tell us about your plot. We reply during office hours (IST).